MCQ
Q.
Requirements Management has a high initial start-up cost but does not need ongoing funding throughout a project.
Correct Answer: B
Requirements Management needs continued funding throughout a project.Project funding is often limited at the onset of a project, restricted to those aspects of the project which are tangible and visible, and subsequently allocated in a phase-by-phase manner.