MCQ
Q.
A technique for performing quantitative analysis of progress is known as
Correct Answer: B
The earned value system provides a common value scale for every task, regardless of thetype of work being performed. The total hours to do the whole project are estimated, and every task isgiven an earned value based on its estimated percentage of the total.